KEI operates a gas field called Terang Sirasun Batur (TSB).
The gas is gathered and flows to a FPU for processing, and then exported via a subsea pipeline. It is an obligation of all Indonesian oil and gas operators to perform the Abandonment & Site Restoration (ASR), and to secure the budget in advance in order to be ready and perform the ASR work in the future.
AEM will undertake the ASR for all of the TSB subsea facilities. This includes offshore decommissioning procedures, decomm schedule and cost estimates for a number of scenarios.
FACILITIES
‐ All of Terang Sirasun Batur subsea infrastructure